government to provide it with $ 400 million in aid to invest in the 750MW West Seti Hydropower Project and the transmission line for the project.
The government also has the stake in the project which CWE Investment
Company, a subsidiary of China Three Gorges Corporation (CTGC), has
agreed to develop. As per the revised memorandum of understanding signed
between Investment Board Nepal (IBN) and the Chinese Company on August
27, 2012, the CWE will have 75 percent stake in the project with the
government holding the rest. The Chinese company reportedly agreed to
grant 10 percent stake to the locals of the Far-western region.
As the project requires huge investment, the government sought aid
from the Chinese government, according to government officials. “We
wrote to the Chinese government about one and a half weeks ago, seeking
assistance for the project,” s aid
Hari Pandey, under secretary at the International Economic Cooperation
Coordination Division at the Finance Ministry. “We have asked the
Chinese government to provide as much grant as possible.” The project
cost has been estimated at Rs 160 billion.
According to Pandey, a proposal has also been attached with the letter that mentions the amount that the government
would require to invest in the hydropower project and the transmission
line. As per the proposal, it requires $ 400 million for the purpose.
It requires laying of a 400km-long transmission line to connect the
project’s power to the national grid. During the signing of the MoU, the
IBN and CWE also agreed to take ahead the transmission line project
simultaneously. China Exim Bank and China Development Bank had shown
interest to invest in the transmission line project.
Pandey s aid
that the letter was also to assure the Chinese side that the Nepal
government was serious about the project. “This will encourage the
Chinese company to conclude the power development agreement (PDA) with
the IBN,” he added.
Two months ago, the Chinese company had assured the IBN of its
investment in the project. The IBN is awaiting a response from the
Chinese developer. The IBN is now planning to hold talks with CWE
Investment this week, to move forward the project.
In its letter to the IBN in January-end, the CWE had expressed its
commitment to the 750 MW reservoir project. In its letter, the CWE had
stated that they were in the process to get approval from their board.
It was in response to the IBN letter, committing to resolve the issues
of rehabilitation and resettlement, land acquisition and construction of
the transmission line.
Amid speculation over the West Seti Project, IBN CEO Radesh Pant
claimed that the Chinese company is very much interested in the project.
According to Pant, once the CWE board gives approval, a special purpose
vehicle (SPV) will be established for the construction of the project.
The IBN had earlier taken written commitment from the Ministry of Land
Reforms and Management, the Energy Ministry and the Finance Ministry
that are directly related to the project.