MAY 06 -
Five years ago, the term “national pride projects” was coined and
construction of the infrastructure was launched with generous budget
allocations. Presently, many of these turbocharged schemes are
struggling to survive or progressing at a crawl, if at all.
They had been accorded the highest importance in the budget with huge
resources allocated annually for their construction. They were at the
forefront of the government’s massive development offensive. However,
the country has not much to show after all the hoopla.
The Prime Minister’s Office (PMO), National Planning Commission (NPC)
and line ministries are directly involved in executing the 22
infrastructure projects ranging from roads, electric railways and
hydropower to airports and irrigation.
The government has shovelled Rs 21.50 billion into these projects in
the current fiscal year. In terms of the budget size, the Melamchi
Drinking Water Project has received the largest allocation of Rs 5.24
billion, a twofold increase from the Rs 2.53 billion it got in 2012-13.
However, spending in a majority of the projects has been low as of the
first eight months of the fiscal year. According to the NPC, the
Bhairahawa Regional Airport project has spent just 1.2 percent of its
budget while the proposed Pokhara International Airport has used 0.1
percent of the allocated funds. Similarly, budget expenditure by Bheri
Babai Diversion reached 2.1 percent and by the Postal Road Project 14.3
percent.
Spending by the Pashupati Area Development Trust has been a little
higher at 17.8 percent, and the overall progress of the three
North-South Roads is 36.8 percent.
“Projects making progress above 80 percent are considered good, those
performing below 50 percent are considered bad, while those performing
between 50-80 percent are considered good enough,” said Puspa Lal
Shakya, joint-secretary at the NPC. “Based on this yardstick, the
majority of the national pride projects have performed poorly.”
According to the NPC, substantial progress in spending has been seen at
the Ranijamara Kulariya Irrigation Project, Lumbini Development Fund
and Shikta Irrigation Project with expenditure rates of 82.1 percent,
62.3 percent and 57.3 percent respectively.
Meanwhile, the President Chure Conservation Programme has spent 63.3
percent of its budget, but the NPC said that it had not received its
programme document, and it is not known how much work has been done.
Alarmed by the dismal progress of the national pride projects, Prime
Minister Sushil Koirala has directed the concerned offices to get a move
on. However, the slow pace of construction is not the only issue, the
government has not been able to figure out what is going on at many
projects.
The NPC said in its report to the National Problem Solution Committee,
which is chaired by the Prime Minister, that it could not find out the
actual status of spending at major projects like the Kathmandu
-Tarai Fast Track, East-West Railway, Second International Airport in
Bara, Budhi Gandaki Hydropower Project, West Seti Hydropower Project and
Tamakoshi Hydropower Project. Spending by these projects was dismal
during the first half of the current fiscal year.
Besides allocating huge budgetary funds to these projects, t
he
government has also signed performance contracts with the chiefs of
these projects for better output. A number of them are monitored online
by senior government officials.
Finance Minister Ram Sharan Mahat has stated that the tendency of
allocating lots of money without adequate preparation such as addressing
the issue of land acquisition has resulted in a poor expenditure
pattern at these priority projects.
The Finance Ministry’s half-yearly budget review report said that the
national priority projects had been selected without any solid basis.
Each year, the government added one or two projects under the national
pride project category.
“The number of such projects increased while choosing them at random.
The national pride projects have now just become projects eating up
massive resources with little to show for it,” stated the report.
Among the 22 projects, only one, the Upper Tamakoshi Hydropower
Project, is likely to meet its construction deadline. The oldest among
the pride projects is the Babai Irrigation Project which began in
1989-90 but is nowhere near completion.
The long awaited Melamchi Water Supply Project is back on track, but it
is still difficult to predict whether it will be completed as per its
revised schedule. According to the NPC report, a 135-metre tunnel has
been dug after a new contractor was selected for the project.
According to the NPC report, physical progress of a few projects has
been relatively better than financial progress in the first eight
months. For example, the ambitious Mid-Hill Highway recorded physical
progress of 96.4 percent of the target. “This should be termed good,”
said Shakya.
Regarding the status of the three North-South Highways, track opening
of 11 km of the Koshi Corridor, 10 km of the Kali Gandaki Corridor and
10 km of the Karnali Corridor has been completed. It is 50.4 percent
physical progress, according to NPC.
The physical progress of the Postal Road has been recorded at 8.2
percent. The Postal Road Project ground to a halt after a few
contractors fled, said officials at the Ministry of Physical
Infrastructure and Transport.
The future of Kathmandu
-Tarai Fast Track is stil uncertain. The government is at a loss
regarding how to build this express highway with international firms not
showing much interest. Earlier, it had been decided to develop the
project under the public-private partnership (PPP) model.
As no foreign companies have stepped forward with a concrete proposal,
the government is now considering multiple options for the Fast Track.
One of the options the Ministry of Physical Infrastructure and Transport
has been considering is merging the expressway and the Second
International Airport (SIA) in Nijgadh into one project. An official of
Investment Board Nepal said that if the Fast Track is not built, no
international investor will be attracted to put money in the airport
project at Nijgadh.
The Investment Board is currently looking after the 750 MW West Seti
Hydropower Project which looks like getting delayed as the developer CWE
Investment Company, a subsidiary of China Three Gorges Corporation
wants to do a pre-feasibility study which government officials say is
“unnecessary”.
“During a recent visit to Nepal, officials of China Three Gorges had
informed Investment Board officials that they had been putting off
reaching a decision due to the leadership succession in China. They have
assured us that they will be making a decision on the hydropower
project soon,” said an Investment Board official.
No comments:
Post a Comment