KATHMANDU, MAY 23 -
The Civil Aviation Authority of Nepal (Caan) on Thursday awarded the
contract to build a regional international airport in Pokhara to the
lowest bidder China CAMC Engineering Co. The new airport, which has been
in the works for 39 years, is proposed to be built at Chinnedanda, 3 km
to the east of the existing domestic airport.
Caan’s Director General Ratish Chandra Lal Suman and China CAMC
Engineering’s Chairman and President Lou Yan signed the $ 215.96 million
deal on behalf of their respective governments.
Recurring controversies regarding the price tag have bogged down the
project. Suman had said that he was not comfortable signing the
agreement under the current circumstances. However, the deal went down
after a minister-level decision on Thursday authorised Caan’s director
general to change the tender documents prepared under the Bill of
Quantity (BOQ) to the Engineering Procurement and Construction (EPC)
model, said Birendra Kumar Shrestha, spokesperson of Caan. Under the EPC
model, the contractor becomes liable for completing the project
according to the tender conditions or it ensures the certainty of cost.
“The EPC contract binds the contractor to deliver the project at a
stipulated time with predetermined price regardless of any increase in
costs that the contractor may incur after the contract is signed,” said
Suman.
Following Thursday’s development, Caan is preparing to send a loan
request letter to China EXIM Bank through the Finance Ministry. The
government plans to borrow $ 145 million or more in soft loans from the
bank to build the airport.
Shrestha said that after EXIM Bank sanctioned the loan, the contractor
would conduct a detailed drawing and design of the project. “It will
take at least one year to complete the design and drawing survey of the
project.”
After the completion of the survey, the contractor will submit the
survey details to Caan for its approval. “The project is expected to be
completed in three years after the survey work,” Shrestha said.
On April 7, a Caan board meeting chaired by Tourism Minister Bhim
Acharya approved the project under the revised cost of $ 215.96 million.
The price tag had been recommended by a three-member independent panel
formed by the government.
Caan had invited bids for the project on Feb 9, 2012. The airport
project has been on hold since July 2012 after the lowest bidder China
CAMC quoted a price of $ 305 million, which is 85 percent higher than
the government’s estimate. The government had expected the project to
cost around $ 166 million.
Subsequently, in January 2013, China CAMC wrote to the Tourism Ministry
expressing its willingness to build the project at the
government-estimated cost.
Things became more complicated after China Airport Construction
Company, a consultant appointed by China CAMC, submitted another study
report to Caan quoting a price of $ 264 million. Adding 16 percent price
escalation and 13 percent VAT, the estimated outlay would come to
around $ 300 million, nearly equal to the original cost quoted by China
CAMC.
Another three-member independent cost evaluation panel recommended a
price of $ 215.96 million. The ministry then tabled the proposal with
the latest estimated cost at the Cabinet, but the Khil Raj Regmi-led
government put the project on the backburner. The project was revived by
Tourism Minister Acharya under the Sushil Koirala-led government. Caan
had even forwarded a separate proposal to the Tourism Ministry asking it
to request the Chinese government to convert the loan pledged by the
Chinese government into a grant.
The government had acquired more than 3,106 ropanis of land in 1975 to
build the airport. It has earmarked Rs 1 billion this fiscal for
additional land acquisition after a fresh study said that another 500
ropanis would be required for the project. As per the feasibility
report, the airport will accommodate medium category jets like the
Boeing 757 and Airbus 320.
No comments:
Post a Comment